New Construction - Lanai and Pool
|
October, 15th - October, 20th
The pool is dug out, prepared with steel supports and poured
with concrete.
|

Click on photo to enlarge
|
|
December,
10th
The outer edge of the pool is tiled.
Underneath this outer edge a second row of tile is adhered.
|

|
|
December, 28th - January,
4th
Stone tile is laid on the terrace/lanai. Several drainage
areas are installed to prevent water from collecting on
lanai.
|
|
|
December, 28th - January,
4th
Above the lanai area a screen (approx 5meters high) is
erected. This screen prevents insects and outside debris,
such as leaves, branches etc) to enter the pool area.
Rain gutters are installed between the roof and screen area.
|

|
February, 15th
A special blue paint is sprayed on the concrete inside walls
and shortly there-after the pool is filled with water.
The pool pump and pool heating system are installed and
hooked up on the side of the home. |

|
March, 4th - March, 11th
The summer kitchen is erected and receives a coat of stucco.
March, 25th - March, 28th
The granite countertop is installed and the grill and
exhaust air fan are fitted and connected. |


|
Driveway and Garden
Phase 4 – End of Construction