New Construction - Phase 4 – End of Construction

 

December, 6th

All inside walls of the showers (wet areas) are now treated with a special, water-resistant paint before the tile can be installed.

 

       Click on photo to enlarge

 

December, 10th - December, 20th

The tile in bathrooms and laundry room is now installed.

 

 

  

 

December, 10th

 

The air duct (air exhaust via roof) for the dryer is installed in laundry room.

20. December, 14th - December, 20th

The sliding doors to the walk-in closet as well as all interior doors are now installed.

 

It is customary that the doors are bare and will not get painted until after installation.



December, 15th and 16th

The automatic garage door system is installed.

This system can be navigated through remote control or on a 4-digit keypad that is installed outside of the garage.

In case of a power outage the garage doors can be opened manually as well.

December, 18th - December, 22th

Tile is now applied in all shower areas. 

January, 10th - January, 31st

The kitchen cabinets are being installed and a wooden platform is erected for the center island.

January, 22nd

Electric outlets/ switches for lighting, cable and telephone are now installed in every room.

February, 27th

Both air conditioning units are installed. Due to the size of this home 2 units with 2 controllable zones are connected.

March, 5th

One of the showers receives a mosaic tile floor.

March, 6th - March, 10th

Now it is time for the parquet wooden floor that is directly adhered to the concrete.

March, 22nd

Control switches for air conditioning system, pool and alarm system are now installed and connected.

March, 24th - March, 30th

The granite countertops in kitchen and baths are installed.

25. March

The temporary front door is replaced by the permanent entrance door and painted after installation.

March, 25th

Door handles on interior doors are installed.

March, 27th

Appliances for kitchen and laundry room are delivered and installed.

March, 28th

The glass shower doors are installed.

March, 27th - 2. April, 2nd

Bathtubs, sinks, toilets and hardware (faucets, knobs etc) are delivered and installed.

Lanai and Pool

Phase 3 - Preconstruction-Inside