New Construction - Phase 3 – Inside Construction
|
September 30th
through
October
15th
The inside walls are being erected and constructed in wood.
For some of the bearing walls metal construction is used.
Wooden support borders approximately
1 inch
in thickness are attached to the outside walls.
|

Click on photo to enlarge
 |
|
October 20th
through
November 20th
One at a time the windows are
installed. They consist of high quality, high impact
glass.(protective glass)
The windows shown in this photo for example lock in 4
different places.
|
|
|
October 20th
through October
25th
Installation of water and sewer lines.
The water and sewer lines underground are extended through
the inside walls, so that all sanitary objects like sink,
showers and toilets can be connected. Sealed PVC pipes are
used for this purpose.
The sewer lines are led through the
inside walls to the top to be connected within the roof
construction and extended over the roof and ventilated on
each side of the house.
|

|
|
October 26th through October 30th
Recessed lighting cans are installed into the roof bars.
Underneath the roof construction all electric wiring for
appliances, tv, phone, alarm system and surround sound are
installed through the inside walls. In order to cover up and
finish the outside walls small slots are inserted.
On the outside wall of the house the electricity meter box
is installed so that the power company may read the power
usage once a month without having to enter the home.
|


 |
October 28th – November 6th
Inside the roof construction all pipes for the air
conditioning system are installed and all devices for the
system are connected.
Inside of the house two condensing units are installed to
give the house two separate climate zones. This equipment
will not only let the owner control the temperature in both
zones but will also reduce the humidity.
The air conditioning system also serves as a heating system. |
|
November 8th
through November, 14th
The entire roof is insulated with spray foam. Once sprayed
into the roof area the foam stretches into an approx. 8 inch
thick insulation within a short time period. This insulation
is applied to the underside of the roof plates in order to
protect the attic as well as all the A/C and electrical
equipment installed there from any harm.
The spray foam is also applied to all holes drilled into the
inside walls up to the ceiling for extra insulation as well
as noise reduction.
The inside walls are insulated with approx. 2.5 inch thick
fiberglass mats.
|

 |
November
16th
-
November
23th
The inside walls and ceilings are now covered with drywall.
|
|
November
23th - November 30th
The seams of the drywall are now hardcoated and areas for
outlets and wall switches are now cut out. |
|