New construction - Phase 2 - Outside
Walls and roofs
|
September 11th and 12th
The outside walls are being built. The
concrete is poured above the windows. Steel bars are being
inserted into the hollow bricks in all corners as well as
every 5’ distance. The cement is poured into the bricks. The
steel bars are taller than the walls and peek out on top.
|
Click once to enlarge the photograph |
|
September 15th through September 17th
An anchor (ring anchor) is poured over
the outside walls. The anchor is then supported with steel
and reinforced with concrete.
Steel bands are added to the anchor every 3’
and these reach approx. 1’ above the anchor and will later be used
to attach the roof bars
|
 |
|
September 18th
through September 23rd
Construction of the roof
Roof construction here in Naples is
slightly different than in Europe or Northern parts of US
since we do not have any heavy snow storms and therefore the
roof bars do not have to be as thick.
During this time one can already see
how the ceilings of the individual living areas will look.
Depending on ceiling height that
changes from children’s rooms (10’ high) to angled ceilings
in living areas (15’ high). The in between areas, visible in
the photo, will be used to run all hoses for the air
conditioning of the home as well as the complex and
elaborate roof insulation.
Every single roof bar is placed on a
sheet of roofing felt to protect from humidity.
The roof bars are connected and reinforced
with steel plates.
|

 |
|
September 24th
through
- 28th
The visible parts of the roof bars are installed. These rise
above the outer walls and will be connected with screws to
the existing roof bars of the construction.
This procedure is the most cost effective since the outside
bars are thicker, high pressure resistant and made out of
substantially harder wood, like pine. |
|
|
September 29th
through October 10th
The roof is covered
with wooden boards. These are nailed to the roof bars.
|
|
October 11th
through October 15th
The ornamental
parts of the roof
are erected. |
|
October 16th
through October 30th
The roof
is sealed with roofing felt and the ornamental elements are
protected with a special foil. |
|
November
10th through November 16th
The outside walls are prepared for paneling and stucco.
|
 |
November
20th through November 24th
The outside panels which consist of a specially developed
plastic are installed. Due to the rain and high humidity
factor in Florida wood is not a good material to use and
would not hold up as well in these weather conditions. The
panels are still unpainted.
|
 |
December
8th
through December
28th
The metal roof is installed and the decorative elements on
the roof are covered.
The panels have now received their first coat of paint. |

 |
Phase 3 - Preconstruction-Inside
Phase 1 - Foundation and Slab